Poulsbo: NE Fox Glove Ln, Phase I Update

Good Morning Poulsbo!

The NE Fox Glove Ln project (Job# 101111445) is continuing Phase I of the project this week and we anticipate this project to wrap up by this week. In phase one, Potelco will install the protective casing underground to house the new cable along the route. You will see large vehicles and crew members in the work area.

Have a great week!

SCHEDULE UPDATE: Weather

Hello Kitsap County!

Current project schedules have been delayed/altered due to weather conditions. Once crews have returned to daily scheduled work we will be sure to post updated schedule information here on the blog.  Thank you for your patience and flexibility.  If you have any questions, please don’t hesitate to post them or use the contact information provided.

Stay safe and warm!

Poulsbo: NE Fox Glove Ln, Phase I Start

Good Morning Poulsbo!

The NE Fox Glove Ln project (Job# 101111445) has begun Phase I of the project this week. In phase one, Potelco will install the protective casing underground to house the new cable along the route. You will see large vehicles and crew members in the work area. We anticipated this project to wrap up by week’s end.

Have a spectacular day!

Poulsbo: NE Gunderson Rd, Phase II Start

Good Morning Poulsbo!

Expect to see a crew working to complete Phase II of the NE Gunderson Rd project (Job# 101111352). In Phase II, a Potelco crew will begin to lay the new electrical cable in the previously installed casing. Some residents may experience a necessary planned power outage so that our crew can safely switch the power from the old cable to the new. We anticipate this project will be completed this week.

Have a fantastic week!

Bainbridge Island: NE Brackenwood Lane, Phase II Start

Good Morning Bainbridge!

Expect to see a crew working to complete Phase II of the NE Brackenwood Lane project (Job# 101111404). In Phase II, a Potelco crew will begin to lay the new electrical cable in the previously installed casing. Some residents may experience a necessary planned power outage so that our crew can safely switch the power from the old cable to the new. We anticipate this project will be completed this week.

Have a fantastic week!