Port Orchard: Eastbrook Dr SW, Phase I Start

Hello Port Orchard!

The Eastbrook Dr SW project (Job# 101117287) is anticipated to begin work on the Phase I portion of this project this week.  In phase one, Potelco will install the protective casing underground to house the new cable along the route. You will see large vehicles and crew members in the work area. We anticipate this portion of the project will last approximately two week.

Have a wonderful Monday!

Port Orchard: Bethel Road, Phase I Continues

Hello Port Orchard,

Work continues on phase I of the Behtel Rd (Job# 101116974) project this week. You will see large vehicles and crew members in the work area as they install the protective casing underground to house the new cable along the route. Don’t hesitate to reach out via the blog or by using any of our provided contact methods should you have any questions. We anticipate working on this project through the week.

We look forward to continuing work in your area.

Port Orchard: Bethel Road, Phase I Continues

Happy Monday Port Orchard,

Work continues on phase I of the Behtel Rd (Job# 101116974) project this week. You will see large vehicles and crew members in the work area as they install the protective casing underground to house the new cable along the route. Don’t hesitate to reach out via the blog or by using any of our provided contact methods should you have any questions.

We look forward to continuing work in your area.

Port Orchard: Orchard Ave, Phase I, complete

Hello Port Orchard!

Our crew should be complete with Phase 1 of the Orchard Ave project (Job# 101111402) this week. In phase one, Potelco installed the protective casing underground to house the new cable along the route. Now that Phase I has been completed, there will be a pause in work before a crew is scheduled to return to begin phase II. Thank you so much for your patience during this project!

We look forward to working in your area!

Port Orchard: Orchard Ave, Phase I, start

Hello Port Orchard!

The Orchard Ave project (Job# 101111402) is anticipated to start today. In phase one, Potelco will install the protective casing underground to house the new cable along the route. You will see large vehicles and crew members in the work area. This phase of the project is expected to last about a week.

We look forward to working in your area!

Port Orchard: Ridge Rim Trail, Phase I, start

Hello Port Orchard!

Our crew should be complete with Phase 1 of the Ridge Rim Trail project (Job# 101111198). In phase one, Potelco installed the protective casing underground to house the new cable along the route. Now that Phase I has been completed, there will be a pause in work before a crew is scheduled to return to begin phase II. Thank you so much for your patience during this project!

We look forward to working in your area!

Port Orchard: Puget Drive, Phase I, complete

Hello Port Orchard!

Our crew should be complete with Phase 1 of the Puget Drive project (Job# 101111409) this week. In phase one, Potelco installed the protective casing underground to house the new cable along the route. Now that Phase I has been completed, there will be a pause in work before a crew is scheduled to return to begin phase II. Thank you so much for your patience during this project!

We look forward to working in your area!

Port Orchard: Puget Drive, Phase I, start

Hello Port Orchard!

The Puget Drive project (Job# 101111409) is anticipated to start this week. In phase one, Potelco will install the protective casing underground to house the new cable along the route. You will see large vehicles and crew members in the work area. This phase of the project should last about a week.

We look forward to working in your area!