Schedule Update: COVID-19

As the COVID-19 pandemic continues, we have temporarily paused Cable Remediation work in your area in effort to do our part to slow the spread of the Coronavirus. The health and safety of our customers, employees, subcontractors and the public are always our number one priority. This temporary pause will impact work that may have begun in your area or is scheduled to begin this Spring. We will post updates here on the blog for all projects in your area as this situation develops, as well as post when a project has been rescheduled.

Thank you for your patience as we continue to bring you safe and reliable electrical upgrades. Should you have any questions or concerns surrounding a project in your neighborhood, feel free to contact the coordinator below. We look forward to working in your community again soon.

 

Stephanie Power
Lead Communications Coordinator
Potelco, Inc.
253-307-5601
sjpower@potelco.net

 

 

Bremerton: Lebo Blvd, Phase I Start

Good Morning Bremerton!

The Lebo Blvd project (Job# 101116792) has begun and is anticipated to wrap up with Phase I of the project late March.  In phase one, Potelco will install the protective casing underground to house the new cable along the route. You will see large vehicles and crew members in the work area.

Have a wonderful Tuesday!

Bremerton: NE Athens Ct, Phase I Update

Good Morning Bremerton!

The NE Athens Ct project (Job# 101116818) continues and is anticipated to wrap up with Phase I of the project this week.  In phase one, Potelco will install the protective casing underground to house the new cable along the route. You will see large vehicles and crew members in the work area.

Have a wonderful Monday!

Bremerton: Kitsap Way, Phase II Update

Good Morning Bremerton!

Expect to see a crew working to complete Phase II of the Kitsap Way project (Job# 101117065). In Phase II, a Potelco crew will begin to lay the new electrical cable in the previously installed casing. Some residents may experience a necessary planned power outage today between 9am-2pm so that our crew can safely switch the power from the old cable to the new. We anticipate this project will be completed this week.

Have a great Thursday!

Port Orchard: Jackson Ave SE, Phase II Update

Good Morning Port Orchard!

Expect to see a crew working to complete Phase II of the Jackson Ave SE (Job# 101116951). In Phase II, a Potelco crew will begin to lay the new electrical cable in the previously installed casing. Some residents may experience a necessary planned power outage today between the hours of 9am – 12pm so that our crew can safely switch the power from the old cable to the new. We anticipate this project will be completed this week.

Have a great day!

Bremerton: Kitsap Way, Phase II Update

Good Morning Bremerton!

Expect to see a crew working to complete Phase II of the Kitsap Way project (Job# 101117065). In Phase II, a Potelco crew will begin to lay the new electrical cable in the previously installed casing. Some residents may experience a necessary planned power outage today between 12pm-4pm so that our crew can safely switch the power from the old cable to the new. We anticipate this project will be completed this week.

Happy Wednesday!

Poulsbo: Lofall Ct NW, Phase II Update

Good Morning Poulsbo!

Expect to see a crew working to complete Phase II of the Lofall Ct NW project (Job# 101091948). In Phase II, a Potelco crew will begin to lay the new electrical cable in the previously installed casing. Some residents may experience a necessary planned power outage today between 8:30am-12pm so that our crew can safely switch the power from the old cable to the new. We anticipate this project will be completed this week.

Have a fantastic day!